| Exam ID: 47 |
| |
- 90 multiple-choice questions
- 3½-hour limit
- Open book
|
| Sample Examination Questions: The
sample questions are provided to give you an idea of the
style and format of examination questions. The questions
are not intended to represent content, references or questions
that will be on the examination. They are not intended
nor should they be referenced/used as a study tool for
the examination. |
| 1. |
Pipes or conduits made of _______ shall
NOT be embedded in reinforced concrete unless coated to
prevent electrolytic action. Click for Answer
|
| |
|
A. |
steel |
| |
|
B. |
brass |
| |
|
C. |
copper |
| |
|
D. |
aluminum
|
| 2. |
The method of conveying concrete from the
mixer shall: Click for Answer
|
| |
|
A. |
be as rapid as possible. |
| |
|
B. |
be done with steel chutes. |
| |
|
C. |
prevent separation and loss of materials. |
| |
|
D. |
be started within 90 minutes of arrival at the jobsite.
|
| 3. |
Who shall the special inspector first notify
when discrepancies are observed? Click for Answer
|
| |
|
A. |
The contractor. |
| |
|
B. |
The building official. |
| |
|
C. |
The testing laboratory. |
| |
|
D. |
The architect or engineer of record.
|
| 4. |
Immediately before placing fresh concrete
against previously placed (hardened) concrete at a construction
joint, the surface of the hardened concrete shall be:
Click for Answer
|
| |
|
A. |
dried. |
| |
|
B. |
wetted. |
| |
|
C. |
roughened. |
| |
|
D. |
coated with a bonding agent.
|
| 5. |
The minimum inside diameter of bend
for a No. 8 bar size, other than for stirrups and ties,
is ______ bar diameters. Click for Answer
|
| |
|
A. |
3 |
| |
|
B. |
4 |
| |
|
C. |
6 |
| |
|
D. |
8
|
|
|
|
|