| 01. |
GENERAL ADMINISTRATION (Content Area) |
2% |
| |
0101. Public Information (Task) 2%
Provide general information on code provisions
and communicate using proper code definitions
and terminology with co-workers and with individuals
who submit plans. |
|
| 02. |
SERVICES
(Content Area) |
24% |
| |
0201.
Service Size, Rating (Task) 8%
Determine code compliance of service equipment including
the riser diagram, the location, number of disconnects,
feeders, clearances, location, and materials. |
|
| |
0202.
Service Grounding and Bonding (Task) 7%
Determine code compliance of the service grounding
and grounding electrode system including the size,
type of conductors, location and electrodes. |
|
| |
0203.
Load Calculations (Task) 6%
Determine code compliance of the size of service
conductors for single phase loads, three phase loads
and combination of single and three phase loads. |
|
| |
0204. Fault Current Calculations and Current
Limiting Characteristics (Task) 3%
Determine code compliance of the current limiting
characteristics of the service equipment and maximum
fault current available considering the size and
impedance of the system. |
|
| 03. |
BRANCH
CIRCUIT & FEEDER REQUIREMENTS (Content Area)
|
19% |
| |
0301.
Feeder Calculations (Task) 5%
Determine code compliance of size of feeder conductors
and verify the feeder load calculations. |
|
| |
0302.
Branch Circuit Calculations (Task) 4%
Determine code compliance of branch circuit loads
and conductor size. |
|
| |
0303.
Branch Circuit Ratings and Overcurrent Protection
(Task) 5%
Determine code compliance of size, type, and location
of overcurrent devices including overcurrent protection
for tap conductors. |
|
| |
0304. Equipment Grounding and Bonding (Task)
5%
Determine code compliance of size, type, and location
requirements for grounding of equipment. |
|
| 04. |
WIRING
METHODS AND DISTRIBUTION SYSTEMS (Content Area)
|
11% |
| |
0401.
Branch Circuit Requirements (Task) 3%
Determine code compliance of the number of branch
circuits, receptacle, lighting and appliance outlets
and verify that GFCI and AFCI protection is provided
where required. |
|
| |
0402.
Boxes and Enclosures (Task) 2%
Determine code compliance of boxes and enclosures,
verifying they are the proper type, material and
correctly sized. |
|
| |
0403.
Panelboards and Switchboards (Task) 4%
Determine code compliance of panelboards and switchboards
and verify the location, clearances and rating. |
|
| |
0404. Raceways, Cables and Bus Ducts (Task)
2%
Determine code compliance of wiring methods. Verify
proper sizing/fill of raceways. |
|
| 05. |
EQUIPMENT
FOR GENERAL USE (Content Area) |
15% |
| |
0501.
Switches, Receptacles and Lighting Fixtures (Task)
3%
Determine code compliance of lighting fixtures,
type and rating of receptacles, switches and disconnects. |
|
| |
0502.
HVAC Equipment and Other Appliances (Task) 3%
Determine code compliance of heating and cooling
equipment, and appliances. |
|
| |
0503.
Motors and Controllers (Task) 5%
Determine code compliance of motors and motor controllers
and motor branch circuits. Verify calculations for
locked rotor current, short circuit protection for
motor branch circuits, overload protection for motors
and disconnects. |
|
| |
0504. Transformers, Generators and Miscellaneous
Equipment (Task) 4%
Determine code compliance of other general use
equipment such as generators and transformers. |
|
| 06. |
SPECIAL
OCCUPANCIES (Content Area) |
16% |
| |
0601.
Hazardous Locations (Task) 5%
Determine code compliance of wiring methods, materials
and equipment for use in hazardous locations. |
|
| |
0602.
Health Care Facilities (Task) 4%
Determine code compliance of electrical wiring for
health care facilities. |
|
| |
0603.
Miscellaneous Other Special Occupancies (Task) 3%
Determine code compliance of electrical wiring for
other special occupancies to verify compliance with
special code requirements including mobile homes
and RV parks. |
|
| |
0604. Commercial Garages, Gas Stations (Task)
4%
Determine code compliance of wring methods and
materials for commercial garages, gas stations,
bulk storage plants and similar hazardous locations. |
|
| 07. |
SPECIAL
EQUIPMENT (Content Area) |
7% |
| |
0701.
Swimming Pools, Fountains and Similar Installations
(Task) 4%
Determine code compliance of wiring methods and
equipment for swimming pools, spas, indoor installations
of decorative fountains and similar installations. |
|
| |
0702. Miscellaneous Special Equipment (Task)
3%
Determine code compliance of wiring and equipment
for miscellaneous special equipment including
signs, Information Technology Rooms and wiring
and equipment for fire protection systems including
fire pumps. |
|
| 08. |
SPECIAL
SYSTEMS (Content Area) |
6% |
| |
0801.
Emergency and Standby Systems (Task) 3%
Determine code compliance of emergency systems including
egress lighting and exit signs. |
|
| |
0802.
Signaling Systems (Task) 1%
Determine code compliance of Class 1, 2, and 3 circuits. |
|
| |
0803. Fire Alarm Systems (Task) 2%
Determine code compliance of fire alarm system
wiring and devices. |
|