Exam ID: VI
 
  • 60 multiple-choice questions
  • 1½-hour limit
  • Open book
Content Outline: A detailed outline of the subject matter covered by the exam, including the percentage of questions from each content area and task.
 
Number of questions
01. Vapor Recovery Systems Pre-installation
9
  0101. Licenses & Certification
Obtain required permits, licenses and certifications.
 
  0102. Executive Orders
Comply with CARB Executive Orders.
 
  0103. Manufacturer's Specifications
Read and following manufacturer's installation specifications.
 
  0104. Vapor Recovery System Identification
Identify vapor recovery systems and components.
 
02. Installation of Below Grade Vapor Recovery Components
19
  201. UST System Layout
Verify site layout for all piping including vent and vapor piping.
  202. Approved Materials
Verify that proper materials are installed.
  203. Installation of Vapor Recovery Components
Install piping and assemble components in accordance with manufacturer's specifications and Executive Orders.
  204. Overfill Prevention
Verify installation of overfill protection.
  205. Secondary Containment
Install secondary containment vapor and vent piping.
03. Installation of Above Grade Vapor Recovery Components
17
  301. Dispenser and Dispenser Vapor Piping
Install dispenser and dispenser vapor piping.
  302. Vacuum Assist Systems and Processors
Install vacuum assist systems, vacuum motors, and/or processor.
  303. Hanging hardware
Install hanging hardware.
  304. Vent Risers and Pressure Vacuum Valve
Install vent risers and pressure vacuum valve.
04. Repair of Vapor Recovery System Components
8
  401. Observation and Trouble Shooting
Observe the equipment to determine or identify the source of the problem.
 
  402. Repair Replace Components
Repair or replace affected components.
  403. System lock-out/tag-out procedures
Follow System lock-out/tag-out procedures when necessary.
05. Safety
7
  501. Leak and Spill Prevention
Use procedures to prevent spills and releases.
  502. Emergency Response
Locate emergency shut-off switch, fire extinguishers, fire suppression systems and use appropriate emergency response procedures.
 
  503. Vapor and Sources of Ignition at Job Site
Identify and remove sources of ignition and maintain vapors at safe levels.
  504. Personal and Site Safety Equipment
Use necessary equipment such as eye protection, safety vests, caution tape and other safety equipment.
  505. Confined Spaces
Identify and follow safety precautions for confined spaces.

Return to certification category

 

 

 

Contact Information

1-888-ICC-SAFE (422-7233), ext.
Certification Examinations
33806
Certification Renewal
33815
MCP Certification Examinations
33806
CBO Examinations
33806
Contractor Examinations
33805
Legacy Examinations
33823
UST/AST Examinations
33823
Special Inspection Examinations
33823



Click for more information

 

 
Home | Membership | ICC Store | Codes & Standards | Government Relations
Training | Certification & Testing | Public Safety | Jobs & Code Talk | Newsroom & Magazine
Contact Us | Privacy Policy | Vision, Mission & Values | Blueprint to the Future
Subsidiaries: ICC Evaluation Service | International Accreditation Service | ICC Foundation
© 2008 International Code Council

 

About ICC ICC Board Site Map Contact Us Help