      • Buildings, Construction, Architecture/Design
      • Fire, Wildland-Urban Interface
      • Plumbing, Mechanical, Fuel Gas, Pools/Spas
      • Energy, Solar, Green, Sustainability
      • Disaster Preparedness, Mitigation, Resiliency
  • Subscribe
    • ICC Family of Solutions
    • ICCSafe
    • myICC
    • Digital Codes
    • cdpACCESS
    • Store
    • Support

Join today!

Keep up-to-date on crucial industry news, innovative training and expert technical advice with a free subscription to the award-winning Building Safety Journal.

Subscribe

Sign In or Register Here

Provide your email address
Provide your password
Answer the math challenge
Please enter your e-mail address below. We will email you a link to reset your password.
Provide your email address
Answer the math challenge
To complete your registration, please verify your email address.
Answer the math challenge

We have emailed the address you provided. Please click the link in the email to confirm your email address.

Your account has been marked for password reset. Please change your password.
Provide your new password
Verify your new password
Answer the math challenge 3 plus two

Only registered ICC members have access to this article at this time.

Explore all the benefits that ICC Membership has to offer and become a member today to gain access to this exciting content.

If you're already an ICC member Sign In Now.

Can We Help?

  • Reset My Password
  • I Need More Help

Water heater safety in the International Codes

May 13th, 2019
by Charles Lee Clifton
  • Technical Topics

The location of a water heater is always a concern. Many are installed inside a living space and tucked away in a closet. It doesn’t take much imagination to envision what could happen when one of these water heaters is not installed properly. A water heater temperature and pressure relief valve is an important safety device for water heaters as well as the water distribution system to which it is connected. A new edition of CodeNotes — Water Heater Safety in the I-Codes (based on the 2018 IPC and IRC) — provides an understanding of the detailed requirements on these items from an overall safety viewpoint.

Water Heater Temperature and Pressure Relief Valve

water heater pressure relief valve discharge pipe codeThe water heater installed in a home can be a ticking time bomb if not installed correctly or maintained properly. A water heater temperature and pressure relief valve is an important safety device for water heaters as well as the water distribution system to which it is connected. If the water heater is operating properly, the pressure in the water distribution system is no greater than is required by the code, and the relief valve is in proper operating condition, then there should not be any water discharge from the relief valve. Any water discharge from the relief valve is an indication of a water distribution system problem, a water heater problem or that the relief valve is malfunctioning.

Code Requirements for Relief Valves

There are other important items associated with the relief valve. These items are mentioned in Section 504.6 of the International Plumbing Code (IPC) and Section P2804.6.1 of the International Residential Code (IRC). These sections address the requirements of discharge piping serving a pressure relief valve, temperature relief valve or combination temperature and pressure relief valve. Because the discharge piping from these safety devices that serve water heaters are an extension of the potable water distribution system, the outlet of the discharge pipe must be treated as a potable water supply system outlet.

Discharge pipingRelief Valve DischargeItem 1 states the discharge piping not be directly connected to the drainage system. Although an air gap is already required for the protection of the potable water supply in Section 608.16.1, a plumber or other authorized installer might not realize that the termination point of the relief valve discharge pipe shall also provide for an airgap.

Item 2 requires the discharge to terminate through an air gap located in the same room as the water heater. (See Figure 1)

Item 3 requires the discharge piping not be smaller than the diameter of the outlet of the valve served and must discharge full size to the air gap. (See Figure 2)

Item 4 requires the discharge piping serve only a single relief device and that it shall not connect to piping serving any other relief device or equipment. Figure 3 illustrates an approved means of connecting the discharge from multiple water heater relief valves. The code is silent as to the size or shape of the waste receptors and the gravity drain line size for capturing and conveying the discharge water from relief valves.

Connecting the discharge from multiple water heater relief valveDischarge terminating to the pan.Item 5 requires that the discharge piping serving relief valves, discharge to the floor, to the pan serving the water heater or storage tank, to a waste receptor or to the outdoors. Figure 4 illustrates the discharge terminating to the pan.

Item 6 requires the discharge piping to discharge in a manner that does not cause personal injury or structural damage. A good example of locations that are not suitable for the termination of relief valve drain lines are shower floors, laundry trays, kitchen sinks, and bath tub. Anyone that would be using these fixtures could be subject to injury by hot water and steam that could come from the pipes.

Item 7 requires the discharge to terminate to a point that is readily observable by the building occupants. It is important that the occupant be aware of the discharging relief valve or valves as soon as possible to limit the amount of discharge that may possibly cause damage or injury.

Items 8 and 9 require the relief valve discharge line to not be trapped and must drain by gravity without sags in the piping. Retained water in these trapped areas or piping sags might cause a buildup of scale or corrosion over time, or possibly freeze if the piping is located in an area that is subject to freezing. Both situations have the potential to create a blockage to any discharge that might come from a relief valve which would create a dangerous condition.

Item 10 requires the relief valve to terminate no more than 6 inches (152mm) above the floor surface, a waste receptor or floor drain in order to prevent hot water discharge from being directed onto a building occupant that may be nearby. Obviously for termination points to the floor, the floor must be a suitable location for water discharge or a floor drain or waste receptor must be provided to capture and direct discharges from the pipe. See Figure 5 for example of approved and unapproved termination.

Item 11 requires the discharge piping have no threaded connection at the end of such piping. This would make it easy for someone to screw on a cap or valve to stop the dripping water from the pipe. What might be perceived as an easy repair by the handy person could create a dangerous situation that could result in severe damage of the building and injury or death of the occupants. (See Figure 6)

Item 12 prohibits discharge pipes from having valves or tees installed. The valve and tee fittings are obviously prohibited as the valve can be closed creating a dangerous situation and the tee fitting could allow connections of piping from other sources. (See Figure 7)

Relief valve approved and unapproved termination.Lack of connection on valveprohibited discharge pipes with valves or tees installedItem 13 requires that discharge piping be constructed of materials listed in Section 605.4 or materials tested, rated and approved for such use as in accordance with ASME A112.4.1. Piping material that comes in contact with potable water is required to conform to NSF 61. Pipe installed in a water distribution system must be capable of withstanding the working pressure of the system at the maximum hot water temperature that could be present in the system. The discharge piping shall have a pressure rating of not less than 100 psi (690 kPa) at 180°F (82°C). The reason the maximum working pressure for the pipe is set at 100 psi (690 kPa) is because of the possibility of pressure surges in a water distribution system.

Importance of Proper Installation Requirements

To summarize, the installation requirements of discharge piping serving a pressure relief valve, temperature relief valve or combination temperature and pressure relief valve mentioned in Section P2804.6.1 of the IRC and Section 504.6 of the IPC are extremely important. If not installed as required by this code could result in contamination of the potable water supply system and or create a very dangerous situation that could result in explosion.

 


 

As part of its goal to serve the needs of plumbing, mechanical and fuel gas (PMG) officials, the ICC PMG Official Membership Council is committed to providing free, informative code support documents known as CodesNotes that can be used to complement building departments’ in-house weekly supplemental training. We hope you enjoy this newest edition of CodeNotes. Past topics include backflow devices and the protection of the water supply, gas pipe sizing based on the latest edition of the International Fuel Gas Code and the International Residential Code, and bonding of corrugated stainless steel tubing gas piping systems, just to name a few. The CodesNotes collection has recently been expanded to include a selection of notes offered in Spanish.

The ICC PMG Official Membership Council website offers many resources. The council — open to all ICC members and serving the needs of PMG officials and industry professionals — consists of a great team of professionals who are willing to share their technical expertise and experiences. You’ll have the opportunity to discuss issues that you face as a community, and how ICC might best serve you. If you haven’t already done so, please go online and become a member of the PMG Official Membership Council.


Untitled Document
Get building safety news delivered to your inbox! Subscribe now to the latest news on a variety of topics.
JutTZtF6gaxlomiqAPYGoNhsvwcFqa114y5qGFfBluI=.html
 

About the Author
Charles Lee Clifton
Charles Lee Clifton, retired senior director of plumbing, mechanical and fuel gas resources for the International Code Council, has more than 45 years of experience in the plumbing, mechanical and fuel gas industry. His career began as a second-generation plumber, working for his father at Clifton Plumbing Inc., in Tampa, Florida. He retired from the city of Los Angeles in 2007 as a principal inspector after 21 years of service. He retired from the International Code Council after 13 years of service.
Submissions
Check out upcoming BSJ topics and send us articles for consideration:
Or send by email

Want to advertise in the BSJ?
Click Here

Share on Facebook
Facebook
Tweet about this on Twitter
Twitter
Share on LinkedIn
Linkedin

  • 25 24731 BSM BSJ Website 270x270 WAD FINAL
  • 25 24651 TRN WDS BSJ BSJW WAD 270x270 FINAL a
  • 24 24393 TRN Learn Live Subscription BSJ AD 270x270 FINAL c
  • tile 3
  • 25 24699 PD TRN SKGA Sub Plan BSJ WAD FINAL 270 x 270 2
International Code Council
International Code Council
International Code Council
International Code Council

Subscribe to the Building Safety Journal

Subscribe

Connect with Us

  • LinkedIn
  • Facebook
  • X
  • YouTube
  • Instagram

ICC Family of Solutions

  • Privacy Policy
  • Terms of Use
  • Contact Us
  • Accessibility Policy
JutTZtF6gaxlomiqAPYGoNhsvwcFqa114y5qGFfBluI=.html